    LIKONI CDAC Community Projects Baseline Information Gaps, Outputs, Outcomes and Impact

    Project One: Construction of Two Classrooms – Mrima Primary School

    School overpopulated more than 100 per class (Verification)

    Exposure to COVID 19 Risks and related diseases

    Overpopulation affecting teacher – student ratio hence affecting quality of teaching and performance.

    Likoni sub county is a VE hotspot and, many kids including those in primary and secondary schools are radicalized and involved in juvenile criminal activities, drug abuse and general VE.

    Information Gaps:

    Factual figures of student totals per class segregated into male female

    Factual data on school entry behaviour, school dropout behaviour and successful school completion trends and secondary school transition behaviour

    How many primary schools in area Timbwani?

    Birth rate Timbwani, Number of households

    Status of youth engagement in jobs and other economic activities based on academic performance and successful transition to institutions of higher learning and professional development.

    Recommended Action:
    Head teacher to give factual figures of total number male and total female per class – School entry behaviour and school exit behaviour –

    Sub County Education Office

    For Birth rate data contact Sub County Health Office

    Number of Households and Birthrate – KNBS – Health / IEBC

    Photos required

    Short video

  • VIREC

    Construction of Administration Block – Longo Primary School

    The head teacher does not have an office – old administration block dilapidated and condemned by health officials.

    Currently occupying a classroom taken away from students. Again exerts pressure and inconveniencing students. Classroom also leaking

    Information Gaps:

    Photos required

    Short video

  • VIREC

    Construction of Two Classrooms – Vyemani Primary School

    School overpopulated more than 100 per class (Verification)

    Exposure to COVID 19 Risks and related diseases

    Overpopulation affecting teacher – student ratio hence affecting quality of teaching and performance.

    Likoni sub county is a VE hotspot and ,many kids including those in primary and secondary schools are radicalized and involved in juvenile criminal activities, drug abuse and general VE.

    Information Gaps:
    Factual figures of student totals per class segregated into male female

    Factual data on school entry behaviour, school dropout behaviour and successful school completion trends and secondary school transition behaviour

    How many primary schools in area Timbwani?

    Birth rate Timbwani, Number of households

    Status of youth engagement in jobs and other economic activities based on academic performance and successful transition to institutions of higher learning and professional development

    Recommended Action:
    Head teacher to give factual figures of total number male and total female per class – School entry behaviour and school exit behaviour –

    Sub County Education Office

    For Birth rate data contact Sub County Health Office

    Number of Households and Birthrate – KNBS – Health / IEBC

    Photos required

    Short video

  • VIREC

    Construction of Three Classrooms – Maji Safi Primary School

    School overpopulated more than 100 per class (Verification)

    Exposure to COVID 19 Risks and related diseases

    Overpopulation affecting teacher – student ratio hence affecting quality of teaching and performance.

    Likoni sub county is a VE hotspot and ,many kids including those in primary and secondary schools are School overpopulated more than 100 per class (Verification)

    Exposure to COVID 19 Risks and related diseases

    Overpopulation affecting teacher – student ratio hence affecting quality of teaching and performance.

    Likoni sub county is a VE hotspot and ,many kids including those in primary and secondary schools are radicalized and involved in juvenile criminal activities, drug abuse and general VE.
    and involved in juvenile criminal activities, drug abuse and general VE.

    Information Gaps:
    Factual figures of student totals per class segregated into male female

    Factual data on school entry behaviour, school dropout behaviour and successful school completion trends and secondary school transition behaviour

    How many primary schools in area Timbwani?

    Birth rate Timbwani, Number of households

    Status of youth engagement in jobs and other economic activities based on academic performance and successful transition to institutions of higher learning and professional development.

    Recommended Action:
    Head teacher to give factual figures of total number male and total female per class – School entry behaviour and school exit behaviour –

    Sub County Education Office

    For Birth rate data contact Sub County Health Office

    Number of Households and Birthrate – KNBS – Health / IEBC

    Photos required

    Short video

    December 28, 2021 at 5:4

  • VIREC

    Construction of Modern Kitchen and Dining Hall with Customized Access Ramp for PWDs – Mtongwe Primary School.

    Lack of a proper kitchen and adequate catering facilities, affecting efficiency, quality of food and hygiene standards. Students with special needs require quality food, and timely feeding to avoid wastage of time affecting classroom learning schedule. One of few cerebral pulse centres catering for PWDs in the Coastal region Likoni

    More students expected.

    Mitigating Pandemic and hygiene challenges and gaps

    Information Gaps:
    Population

    How current catering services are affecting the students and the school program.

    How the new kitchen facility will change life.

    Get factual info on student population segregated into the different disability forms and the specific challenges the students face in terms of food services.

  • VIREC

    Perimeter Wall – Peleleza Primary School

    Adjacent to ocean line creek Peleleza area is a juvenile gang hot spot area – Currently school exposed to drug abuse maskanis –

  • VIREC

    Water Well Deepening and Installation of Water Distribution Accessories – Mtaa wa Pwani Kibuyuni Bofu

    Old well neglected – revived / colonial period / water available /

    Current source of water – water vendors

    The most adjacent area to the Base Titanium port facility.

  • VIREC

    Water Well Deepening and Installation of Water Distribution Accessories Integrated with commercial water vending opportunities for economic empowerment of youth and women– Likoni Stadium, Likoni Pry School, Kindunguni Dispensary and Masjid Khadija Community

    Huge community population depending on this water source, including Likoni pry school, Kindunguni dispensary, Likoni stadium and Masjid Khadija and community neighborhood.

    Information Gaps:
    Student population

    Confirms water needs and frequency of water usage by the stadium facility.

  • VIREC

    Waste Recycling Facilities in each of the 5 Wards

    There is a huge garbage problem in Likoni Sub County creating a sanitation problem

    Project to help generate solutions for the waste menace and in the process create economic empowerment for the youth.

    Diseases outbreak due to waste dumping

    Youth economic empowerment to mitigate idleness and build resilience against push pull VE factors.

    Information Gaps:
    Number and location of dumpsites in each ward and a build a clear picture of the problem and how it is affecting the people.

  • VIREC

    Women and Youth Economic Fund and Blue Economy Initiatives

    Poverty among youth and women (Statistics needed)

    Correlation between poverty and crime

    Bring out existing blue economy opportunities in Likoni and the opportunities to be exploited for economic empowerment by the youth and women.

  • VIREC

    Project Implementation Work Plan

    Construction of Two Classrooms – Mrima Primary School – FY 2020/2021 – Quarter One – KSH 5,230,000 – Start Date and End Date (Details to be sought from Base Titanium)

    Construction of Administration Block – Longo Primary School – FY 2020/2021 – Quarter One – KSH 4,900,000 – Start Date and End Date (Details to be sought from Base Titanium)

    Construction of Two Classrooms – Vyemani Primary School – FY 2020/2021 – Quarter Three – KSH 5,500,000 – Start Date and End Date (Details to be sought from Base Titanium)

    Construction of Three Classrooms – Maji Safi Primary School – FY 2020/2021 – Quarter Three – KSH 9,000,000 – Start Date and End Date (Details to be sought from Base Titanium)

    Construction of Modern Kitchen and Dining Hall with Customized Access Ramp for PWDs – Mtongwe Primary School – FY 2020/2021 – Quarter Two – KSH 11,300,000 – Start Date and End Date (Details to be sought from Base Titanium)

    Perimeter Wall – Peleleza Primary School – FY 2020/2021 – Quarter Two – KSH 5,700,000 – Start Date and End Date (Details to be sought from Base Titanium)

    Water Well Deepening and Installation of Water Distribution Accessories Integrated with commercial water vending opportunities for economic empowerment of youth and women– Likoni Stadium, Likoni Primary School, Kindunguni Dispensary and Masjid Khadija Community – FY 2020/2021 – Quarter Two – KSH 2,300,000 – Start Date and End Date (Details to be sought from Base Titanium)

    Water Well Deepening and Installation of Water Distribution Accessories – Mtaa wa Pwani Kibuyuni Bofu – FY 2020/2021 – Quarter Two – KSH 1,500,000 – Start Date and End Date (Details to be sought from Base Titanium)

    Waste Recycling Facilities in each of the 5 Wards – FY 2020/2021 – Quarter Four – KSH 5,000,000 (each ward) – Start Date and End Date (Details to be sought from Base Titanium)

    Women and Youth Economic Fund and Blue Economy Initiatives – FY 2020/2021 – Quarter Four – KSH – Start Date and End Date (Details to be sought from Base Titanium)

    • VIREC

      Construction of Two Classrooms – Mrima Primary School – FY 2020/2021 – Quarter One – KSH 5,230,000 – Start Date and End Date (Details to be sought from Base Titanium)

      Activities:

      Public participation

      Prioritisation

      Budgeting

      Community feedback

      Project beneficiary visits

      Formation of Project Committee

      Bidding, Evaluation & Awarding

      Project Implementation and Continuous Monitoring

      Project handover

      Success Story Harvesting, Documentation and Continuous Community Feedback

      Outputs:

      12 community engagements meetings conducted.

      Draft development agreement document prepared.

      Projects of high interest considered according to community needs.

      2 days CDAC meeting conducted

      Budget estimates for each prioritized project determined.

      6 community engagement meetings conducted

      Prioritized projects and budget estimates approved by the community.

      Project committee formed ()

      Site visit conducted and specific local project committee formed

      Expression of interest and quotations received from bidders (At least 3 as per the policy)

      Contract awarded, Construction site identified, construction started, monthly project monitoring sessions

      Site visit with interested contractors before bidding.

      Bids received, evaluated and awarded.

      Winning bidder introduced to the project committee

      Outcomes:
      2 classrooms constructed and handed over to the school management.

      Impact:
      KCPE performance improved due improved learning environment – Number of students transitioning to good secondary schools improved – transition to institutions of higher learning increased – more youth constructively engaged in economic activities – crime rate lowered.

    • VIREC

      Construction of Administration Block – Longo Primary School – FY 2020/2021 – Quarter One – KSH 4,900,000

      Activities:

      Public participation

      Prioritization

      Budgeting

      Community feedback

      Project beneficiary visits

      Formation of Project Committee

      Bidding, Evaluation & Awarding

      Project Implementation and Continuous Monitoring

      Project handover

      Success Story Harvesting, Documentation and Continuous Community Feedback

      Outputs:

      12 community engagements meetings conducted.

      Draft development agreement document prepared.

      Projects of high interest considered according to community needs.

      2 days CDAC meeting conducted

      Budget estimates for each prioritized project determined.

      6 community engagement meetings conducted

      Prioritized projects and budget estimates approved by the community.

      Project committee formed ()

      Site visit conducted and specific local project committee formed

      Expression of interest and quotations received from bidders (At least 3 as per the policy)

      Contract awarded, Construction site identified, construction started, monthly project monitoring sessions

      Site visit with interested contractors before bidding.

      Bids received, evaluated and awarded.

      Winning bidder introduced to the project committee

      Outcomes:

      Administration block constructed – Administration functions improved – Classroom returned for use by students

      Impact:

    • VIREC

      Construction of Two Classrooms – Vyemani Primary School – FY 2020/2021 – Quarter Three – KSH 5,500,000

      Activities:

      Public participation

      Prioritization

      Budgeting

      Community feedback

      Project beneficiary visits

      Formation of Project Committee

      Bidding, Evaluation & Awarding

      Project Implementation and Continuous Monitoring

      Project handover

      Success Story Harvesting, Documentation and Continuous Community Feedback

      Outputs:

      12 community engagements meetings conducted.

      Draft development agreement document prepared.

      Projects of high interest considered according to community needs.

      2 days CDAC meeting conducted

      Budget estimates for each prioritized project determined.

      6 community engagement meetings conducted

      Prioritized projects and budget estimates approved by the community.

      Project committee formed ()

      Site visit conducted and specific local project committee formed

      Expression of interest and quotations received from bidders (At least 3 as per the policy)

      Contract awarded, Construction site identified, construction started, monthly project monitoring sessions

      Site visit with interested contractors before bidding.

      Bids received, evaluated and awarded.

      Winning bidder introduced to the project committee

      Outcomes:

      Two classrooms constructed – Social distance improved to mitigate COVID 19 – Learning Environment improved.

      Impact:

      KCPE Performance improved.

    • VIREC

      Construction of Modern Kitchen and Dining Hall with Customized Access Ramp for PWDs – Mtongwe Primary School – FY 2020/2021 – Quarter Two – KSH 11,300,000

      Activities:

      Public participation

      Prioritization

      Budgeting

      Community feedback

      Project beneficiary visits

      Formation of Project Committee

      Bidding, Evaluation & Awarding

      Project Implementation and Continuous Monitoring

      Project handover

      Success Story Harvesting, Documentation and Continuous Community Feedback

      Outputs:

      12 community engagements meetings conducted.

      Draft development agreement document prepared.

      Projects of high interest considered according to community needs.

      2 days CDAC meeting conducted

      Budget estimates for each prioritized project determined.

      6 community engagement meetings conducted

      Prioritized projects and budget estimates approved by the community.

      Project committee formed ()

      Site visit conducted and specific local project committee formed

      Expression of interest and quotations received from bidders (At least 3 as per the policy)

      Contract awarded, Construction site identified, construction started, monthly project monitoring sessions

      Site visit with interested contractors before bidding.

      Bids received, evaluated and awarded.

      Winning bidder introduced to the project committee

      Outcomes:

      Modern kitchen and dining hall with customized access ramp constructed

      Impact:

    • VIREC

      Perimeter Wall – Peleleza Primary School – FY 2020/2021 – Quarter Two – KSH 5,700,000

      Activities:
      Public participation

      Prioritization

      Budgeting

      Community feedback

      Project beneficiary visits

      Formation of Project Committee

      Bidding, Evaluation & Awarding

      Project Implementation and Continuous Monitoring

      Project handover

      Success Story Harvesting, Documentation and Continuous Community Feedback

      Outputs:

      12 community engagements meetings conducted.

      Draft development agreement document prepared.

      Projects of high interest considered according to community needs.

      2 days CDAC meeting conducted

      Budget estimates for each prioritized project determined.

      6 community engagement meetings conducted

      Prioritized projects and budget estimates approved by the community.

      Project committee formed ()

      Site visit conducted and specific local project committee formed

      Expression of interest and quotations received from bidders (At least 3 as per the policy)

      Contract awarded, Construction site identified, construction started, monthly project monitoring sessions

      Site visit with interested contractors before bidding.

      Bids received, evaluated and awarded.

      Winning bidder introduced to the project committee

      Outcomes:

      Perimeter wall constructed – school security improved

      Impact:

    • VIREC

      Water Well Deepening and Installation of Water Distribution Accessories Integrated with commercial water vending opportunities for economic empowerment of youth and women– Likoni Stadium, Likoni Primary School, Kindunguni Dispensary and Masjid Khadija Community – FY 2020/2021 – Quarter Two – KSH 2,300,000

      Activities:
      Public participation

      Prioritization

      Budgeting

      Community feedback

      Project beneficiary visits

      Formation of Project Committee

      Bidding, Evaluation & Awarding

      Project Implementation and Continuous Monitoring

      Project handover

      Success Story Harvesting, Documentation and Continuous Community Feedback

      Outputs:
      12 community engagements meetings conducted.

      Draft development agreement document prepared.

      Projects of high interest considered according to community needs.

      2 days CDAC meeting conducted

      Budget estimates for each prioritized project determined.

      6 community engagement meetings conducted

      Prioritized projects and budget estimates approved by the community.

      Project committee formed ()

      Site visit conducted and specific local project committee formed

      Expression of interest and quotations received from bidders (At least 3 as per the policy)

      Contract awarded, Construction site identified, construction started, monthly project monitoring sessions

      Site visit with interested contractors before bidding.

      Bids received, evaluated and awarded.

      Winning bidder introduced to the project committee

      Outcomes:
      Water well deepened, water tanks and other accessories installed – water scarcity mitigated

      Impact:

    • VIREC

      Water Well Deepening and Installation of Water Distribution Accessories – Mtaa wa Pwani Kibuyuni Bofu – FY 2020/2021 – Quarter Two – KSH 1,500,000

      Activities:

      Public participation

      Prioritization

      Budgeting

      Community feedback

      Project beneficiary visits

      Formation of Project Committee

      Bidding, Evaluation & Awarding

      Project Implementation and Continuous Monitoring

      Project handover

      Success Story Harvesting, Documentation and Continuous Community Feedback

      Outputs:

      12 community engagements meetings conducted.

      Draft development agreement document prepared.

      Projects of high interest considered according to community needs.

      2 days CDAC meeting conducted

      Budget estimates for each prioritized project determined.

      6 community engagement meetings conducted

      Prioritized projects and budget estimates approved by the community.

      Project committee formed ()

      Site visit conducted and specific local project committee formed

      Expression of interest and quotations received from bidders (At least 3 as per the policy)

      Contract awarded, Construction site identified, construction started, monthly project monitoring sessions

      Site visit with interested contractors before bidding.

      Bids received, evaluated and awarded.

      Winning bidder introduced to the project committee

      Outcomes:
      Water well deepened – water tanks and other accessories installed – water scarcity mitigated.

      Impact:

    • VIREC

      Waste Recycling Facilities in each of the 5 Wards – FY 2020/2021 – Quarter Four – KSH 5,000,000 (each ward)

      Activities:

      Public participation

      Prioritization

      Budgeting

      Community feedback

      Project beneficiary visits

      Formation of Project Committee

      Bidding, Evaluation & Awarding

      Project Implementation and Continuous Monitoring

      Project handover

      Success Story Harvesting, Documentation and Continuous Community Feedback

      Outputs:

      12 community engagements meetings conducted.

      Draft development agreement document prepared.

      Projects of high interest considered according to community needs.

      2 days CDAC meeting conducted

      Budget estimates for each prioritized project determined.

      6 community engagement meetings conducted

      Prioritized projects and budget estimates approved by the community.

      Project committee formed ()

      Site visit conducted and specific local project committee formed

      Expression of interest and quotations received from bidders (At least 3 as per the policy)

      Contract awarded, Construction site identified, construction started, monthly project monitoring sessions

      Site visit with interested contractors before bidding.

      Bids received, evaluated and awarded.

      Winning bidder introduced to the project committee

      Outcomes:
      5 recycling facilities acquired and distributed in the five wards (one per ward)

      Impact:
      Garbage menace reduced

    • VIREC

      Women and Youth Economic Fund and Blue Economy Initiatives – FY 2020/2021 – Quarter Four – KSH –

      Activities:

      Public participation

      Prioritization

      Budgeting

      Community feedback

      Project beneficiary visits

      Formation of Project Committee

      Bidding, Evaluation & Awarding

      Project Implementation and Continuous Monitoring

      Project handover

      Success Story Harvesting, Documentation and Continuous Community Feedback

      Outputs:

      12 community engagements meetings conducted.

      Draft development agreement document prepared.

      Projects of high interest considered according to community needs.

      2 days CDAC meeting conducted

      Budget estimates for each prioritized project determined.

      6 community engagement meetings conducted

      Prioritized projects and budget estimates approved by the community.

      Project committee formed ()

      Site visit conducted and specific local project committee formed

      Expression of interest and quotations received from bidders (At least 3 as per the policy)

      Contract awarded, Construction site identified, construction started, monthly project monitoring sessions

      Site visit with interested contractors before bidding.

      Bids received, evaluated and awarded.

      Winning bidder introduced to the project committee

      Outcomes:

      Youth and women running successful livelihood programs and businesses

      Impact:

      Poverty reduced / general living standards improved
      Resilience against radicalization and VE created.

  • VIREC

    Construction of Three Classrooms – Maji Safi Primary School – FY 2020/2021 – Quarter Three – KSH 9,000,000

    Activities:

    Public participation

    Prioritization

    Budgeting

    Community feedback

    Project beneficiary visits

    Formation of Project Committee

    Bidding, Evaluation & Awarding

    Project Implementation and Continuous Monitoring

    Project handover

    Success Story Harvesting, Documentation and Continuous Community Feedback

    Outputs:

    12 community engagements meetings conducted.

    Draft development agreement document prepared.

    Projects of high interest considered according to community needs.

    2 days CDAC meeting conducted

    Budget estimates for each prioritized project determined.

    6 community engagement meetings conducted

    Prioritized projects and budget estimates approved by the community.

    Project committee formed ()

    Site visit conducted and specific local project committee formed

    Expression of interest and quotations received from bidders (At least 3 as per the policy)

    Contract awarded, Construction site identified, construction started, monthly project monitoring sessions

    Site visit with interested contractors before bidding.

    Bids received, evaluated and awarded.

    Winning bidder introduced to the project committee

    Outcomes:

    Three classrooms constructed – learning environment improved – COVID 19 risks mitigated.

    Impact:

    KCPE performance improved